CarCost calculates costs month by month to apply time-limited perks, yearly price growth and multi-phase loans correctly.

Formulas

  • TCO over N years = (car price − residual value after N years) + the monthly sum of energy, maintenance & tyres, insurance, fees & parking and loan interest.
  • Cash cost per km = everything paid (excluding depreciation) ÷ km; true cost per km = TCO ÷ km.
  • EVs: kWh/month = km × kWh/100 km ÷ (1 − charging loss); charger sessions covered by a perk are free up to the cycle’s session quota, the rest is billed at the public price.

Results come from the CarCost engine shared with the app (engine 1.1.0 · data 2026.10.7); every default assumption lists its source and update date below.

Transparent assumptions

Every number has a source

Every assumption shows where it comes from and can be edited. You always know which numbers are defaults, which you entered and which come from the community.

Default
Reference values compiled by CarCost, always with an update date.
Yours
Your own numbers — always take priority.
Community
Anonymous averages from owners of the same model, with sample size (n).
Methodology

Assumptions · VF 6 Plus · Ho Chi Minh City

Tap a row to edit it or view its source

Example assumption set with the source of each parameter
ParameterValueSourceNote
Home electricity₫3,090/kWhDefault
Public charging₫3,858/kWhDefault
Real-world consumption12.8 kWh/100 kmDefault
RON 95 petrol (E10)₫20,990/LDefault
Loan rate/year (first 12 months → after)7.5% → 10.5%Default
Residual value after 5 years≈ 47%Default

Numbers you enter always take priority over defaults and community data.

Free charging

How free charging is counted

CarCost never treats “free” as ₫0 forever: session quotas, cycles and expiry dates are applied to every year of the TCO.

VinFast VF 6 Plus · bought on Mar 12, 2026

V-Green free-charging policy for cars bought from Feb 10, 2026, personal use

Default

V-Green free-charging perks apply to VinFast cars only. EVs of other brands do not get them and pay public charging prices (default: the national average of open networks).

Free · 10 sessions/month at V-Green chargers

Mar 12, 2026 → Feb 10, 2029 · first 35 months

Paid at V-Green prices

From Feb 10, 2029 · assumed ₫3,858/kWh

Mar 12, 2026

Purchase

Feb 10, 2029

Perk ends

Mar 12, 2031

End of year 5

10 sessions / month / car

Counted per charging session, not per kWh. Each cycle runs from the 26th to the 25th of the next month; unused sessions do not roll over.

Cycle Sep 26 – Oct 25: 4/10 used

Over the quota

From session 11 of a cycle, CarCost charges the V-Green price for the exact kWh of that session.

Example: session 11 · 38 kWh × ₫3,858 = ₫146,604

After Feb 10, 2029

Every public charging session becomes paid; energy costs rise from ₫9M to ₫13.8M per year.

Year 4: +₫4.8M vs year 3

Source: manufacturer policy · updated May 18, 2026. CarCost is not affiliated with and does not represent any carmaker or charging network.